By
installing the new EVOTM Conveyor Load Zone from Martin Engineering,
the terminal has increased the average load rate for the entire
ship-loading process from 700 mt/h to 858 mt/h. The terminal has gone
from an absolute maximum of 18,000 mt/d with dry coal and optimal
loading conditions, to more than 20,000 mt/d on average -- including
operations in poor weather and less than ideal operating conditions.
With
throughput increased, ship-loading times are being reduced, driving
down costs and making the exported coal more affordable to overseas
customers. “Basically, we should be able to knock one day off our
loading time for each ship,” observed Steve Denton, VP of Business
Development for Usibelli Coal Mines.
“Over the course of a
million tons per year, that’s a major savings for our customers, as
they’ll be able to enjoy better FOB prices. It also saves us
tremendously on the cost of ship demurrage, which helps us to pay for
the cost of the conveyor investment,” Denton said.
Port a critical linkSince
1985, the Port of Seward has shipped over 16 million metric tons (mmt)
of coal, all of it originating at the Usibelli mine 400 miles to the
north, which currently exports more than 45% of its annual production.
UCM and its affiliate Aurora Energy Services, LLC (operator of the
Seward coal terminal) have no doubt that the port plays a key role in
their future. As one of Alaska’s few year-round ice-free harbors,
Seward is also the southern terminus of the state-owned Alaska
Railroad, and offers terminal facilities -- owned by the railroad and
operated by AES -- with the ship-loading resources to feed the
expanding international export market.
A major obstacle to
expansion was the port facility’s aging infrastructure, which had seen
few improvements prior to 1999. Upgrades began that year when Alaska
Railroad purchased the terminal, but despite best efforts, by 2008 the
facility had become a logistical bottleneck, and with its occasional
dust clouds, also a source of complaint.
The issuesOne
of the issues was the ship-loader itself. With a view to expanding
Usibelli’s export market-share, AES began taking steps to increase
throughput at the Port facility, but initial efforts to reach 2,000
mt/h proved almost entirely unsuccessful. “Working with what we had,
we could only reach 600-700 mt/h,” said AES Terminal General Foreman
Vic Stoltz. “We made some improvements and got up to a steady run rate
of 750 mt/h. But as we did, there were still some major issues with
coal backing up in the chute.”
Even as some gains were
realized, AES found that with higher-speed operation, dust became an
increasing problem. Constructed in a less environmentally-sensitive
era, the ship loader design was not adequate to contain fugitive
material, allowing airborne coal dust to generate negative attention
and threaten community relations.
Combining solutionsThe
need to increase throughput capacity at Seward while protecting the
region’s air quality and natural splendor led AES to investigate new
conveyor technology from Martin Engineering. AES first sent
bucket-sized samples of the typical conveyed material to Martin’s
R&D center in Illinois. After testing the coal to determine its
flow properties, the company’s specialists used Discrete Element Method
modeling to design a chute capable of properly handling the coal.
“When we got back the computer models, we saw that we were able to pass
1500 mt/h and still control dust, all while keeping within our capital
budget,” said Stoltz.
A few months later, Martin Engineering
followed up with an environmental audit while AES was loading a ship,
suggesting improvements to the process. AES decided to implement
several significant modifications, including a new EVO-equipped ship
loading chute. “We knew that we had to do something about the
environmental and production issues that were being caused by this one
chute,” said Stoltz. “When our management realized that we could
increase through-put, increase safety and reduce our environmental
impact all at once, they were completely in favor of implementing the
suggested upgrades.”
A new conveyor architectureThe
new transfer point makes use of Martin® Inertial Flow™ Transfer
Technology, and the entire chute is custom-engineered and modeled in
3-D to provide the optimum design for the material and flow rate
required. The “hood” controls the flow of material from the
discharging conveyor, maintaining a coherent material stream and
minimizing induced air. A smooth loading chute (spoon) places the
stream of coal onto the ship loader’s boom conveyor at the proper speed
and angle with minimal impact, reducing material degradation, belt
abrasion and the expulsion of airborne dust. By controlling the flow
of material, this engineered transfer chute helps eliminate blockages,
shape the load and contain fugitive material.
Martin Engineering
supplied other redesigned components to contain material and improve
serviceability. Belt support cradles were installed under the drop
chute to absorb impact and stabilize the belt line and prevent
spillage. AES also mounted EVO External Wearliner on the load zone’s
existing skirtboard for improved sealing. Because it is attached from
the outside, it is easier to install, inspect and adjust than
conventional seals, without requiring confined space entry.
Pre-engineered
modular chute wall sections simplify the design and construction of the
transfer point stilling zone to manage airflow and control dust. At
the exit end of the load zone structure, dust curtains act as baffles
to slow air movement and allow airborne dust to settle back onto the
conveyor.
Designed to adapt to the unique needs of a specific
facility, the EVO conveyor structure has made the new transfer point
easy to install. Martin shipped everything to Seward by container,
with all components organized, numbered and labeled. “We were able to
easily figure out where everything needed to go,” said Stoltz.
Developed to connect simply and quickly to an existing structure, the
EVO Load Zone took only five days to install and put into service.
ResultsThe
first thing the AES crew noticed was an improved material load rate.
During the initial shakedown run, operators noted the conveyor’s weigh
scale pegged at 100%, but the belt didn’t shut down. The old system
peaked at 1000 mt/h (including ship and hatch moves), but with new
components in place, the system hits peaks of 1500 mt/h.
As
the AES crews have grown familiar with the new equipment, they are
loading even faster. “Loading at the maximum run-rate is a whole new
ballgame for our operators,” Stoltz added. “We don’t have slowdowns
due to the chute clogging up, which previously was a constant battle.”
Immediately
after the first ship was loaded, UCM went through the numbers in the
vessel’s Statement-of-Fact. Excluding crew time, the company found
that the loading rate with the EVO System was 21,000 mt/d, a record for
the terminal and a significant accomplishment.
Equally
important, following the system’s initial run, the ship loading area
was virtually free of fugitive material and dust build-up, allowing AES
crews to reduce their cleanup time from days to just hours. “After the
first boat, all we needed was a dustbin,” said Stoltz. “The clean-up
time has been reduced by over 40 man-hours per shipload.” The company
reports that the recent chute upgrades have virtually eliminated
spillage and dust issues.
Reducing risk To
AES, the environmental and worker safety benefits of Martin
Engineering’s upgrades have been just as important as the production
advantages. “Faster loading times help manage our risk, from both the
environmental and the safety perspective,” commented Bartly Coiley, AES
Manager of Environmental Affairs.
“Poor weather conditions can
and will conspire to generate more dust, so from an environmental
standpoint, the faster you’re able to load, the less risk you have that
weather conditions will impact your loading cycle,” said Coiley. “The
longer it takes to load a ship, the greater the chances of creating
dust.”
Service is critical to a conveyor’s reliability, and
therefore a key to productivity. Situated 90 feet above the waters of
Resurrection Bay, the ship loading area is a very demanding environment
for maintenance personnel, but the EVO load zone is designed for ease
of service and maintenance.
With most components externally
mounted, workers can remove and service most of the system from outside
the conveyor structure, without having to access confined spaces.
“There are fewer safety risks,” said Stoltz. “The access is really
easy, and there are only a couple of occasional adjustments the
operator needs to make.”
“Martin Engineering has gone way beyond
what they had to do, making sure we were more than satisfied,” Stoltz
concluded. “When we first fired up the belts, the systems performed
just as they predicted. Better, in fact. With these upgrades, we’re
earning our money back every time we start the system up.”
Improved loading is key to future growthHaving
an outlet to the ocean is vital for Usibelli. Not only is the export
market consuming virtually half of what the mine currently produces,
the Port of Seward is the mine’s growth gateway to the future.
“Overseas, the market is virtually limitless, and there are signs that
Alaska is being recognized as an international supplier,” said Denton.
Usibelli
coal is sought primarily for its ultra-low sulfur content. “Alaska has
a vast, virtually untapped coal resource,” he explained. “We’re stable
and despite our winters, we don’t have the horrendous weather issues
that some mines have faced. Our customers see that we have large
reserves, that we’re a stable company and that we’re able to ship
predictably.”
And now they can move ships in and out of port
even faster. “The work that Martin Engineering did eliminated a
chronic bottleneck for us. There were many things we were doing to
increase our throughput, but it was impossible to realize the full
benefits until we cleaned up our loading operation with the
installation of the new EVO hood and spoon transfer chute.”
Clean coal-handling technologyThe
improved coal handling system is helping the Seward Coal Terminal
prepare for further growth. The new conveyor load zone on the
terminal’s ship loader has eliminated most environmental issues, which
has been good for the public image of coal in a town that sees a
plethora of tourists each year.
“Because our location is right
next to the cruise ship dock, our facility is almost a tourist
attraction in and of itself,” according to Stoltz. “We get lots of
questions about coal. Folks tell us that they always thought coal
handling was a big mess, but now they can see it doesn’t have to be
that way. After installing the EVO System, the cruise ship passengers
don’t see any dust and even the ship crews couldn’t tell coal was being
loaded.”
Above: With the new conveyor Load
Zone from Martin Engineering, the terminal has increased the average
load rate for the entire ship-loading process from 700 mt/h to 858
mt/h.
Below: To
improve flow and reduce the escape of dust and spillage, Aurora Energy
Services authorized improvements to the ship loader’s boom conveyor.
